Project completion percentage calculator
Project percent complete is the sum of each work item’s weight times its percent complete, divided by the total weight; enter your items and this calculator shows the result, the working and how far you are from plan.
Weight is each item’s budget amount, planned quantity or any number that shows its size. Use one kind for every item.
Project complete
…
Your items are kept in this browser so a reload does not lose them.
How to use it
- Add a row for each work item with its weight: the budget amount is the usual choice, or a planned quantity when every item uses the same unit. Choose equal weights only when the items are similar in size.
- Enter how complete each item is today, from 0 to 100, and the percent your schedule planned for today if you want a comparison.
- Read the weighted percent complete, the worked formula and the gap to plan. Copy the result, or download a CSV or a one-page PDF summary.
The formula, with an example
Percent complete = Σ(weight × percent complete) ÷ Σ weight. Each item counts in proportion to its size, so finishing a large item moves the project more than finishing a small one.
With the four items below the project is 610,000 ÷ 1,000,000 = 61% complete. A plain average of the four percentages would give 47.5%, because it treats the finishes package as if it were as big as the structure.
| Work item | Weight (budget) | % complete | Weight × % |
|---|---|---|---|
| Structure | 400,000 | 100% | 400,000 |
| Envelope | 250,000 | 60% | 150,000 |
| Mechanical and electrical | 200,000 | 30% | 60,000 |
| Finishes | 150,000 | 0% | 0 |
| Total | 1,000,000 | 61% | 610,000 |
Comparing with the plan
If you also enter the percent each item should have reached today, the calculator works out planned percent complete the same way and shows the difference in percentage points. It also divides earned by planned: above 1 means more work is done than planned, below 1 means less. This is the idea behind the schedule performance index in earned value management.
It is a summary measure. It does not tell you whether the late work is on the critical path, so read it next to your programme. Your daily reports are the evidence for why an item is ahead or behind.
Choosing weights and percentages
Budget amounts are the most common weight because they also give the value of work done. Planned quantities only work when every item shares a unit, such as square metres of the same finish. Labour hours are another option on labour-heavy jobs.
For each item, base the percentage on something you can measure: quantity installed ÷ total quantity, or agreed milestones (for example 30% when first fix is done). Estimating by eye tends to run ahead of reality near the end of a job.
Related tools
Questions people ask
How do you calculate percent complete on a construction project?
Give each work item a weight, usually its budget amount, multiply each weight by that item’s percent complete, add the results and divide by the total weight.
Why not just average the percentages?
A plain average treats every item as the same size. A small item at 100% then lifts the project as much as a large one, which overstates or understates progress. Use equal weights only when items are similar in size.
What does earned ÷ planned tell me?
It compares the progress you have with the progress you planned for today. 1.00 is on plan, 1.10 means about 10% more work done than planned, 0.90 about 10% less.
What should I use as the weight for each item?
The budget or contract amount for each item is the usual choice. A planned quantity works only when all items use the same unit. Whatever you choose, use the same kind of weight for every item.
How do I decide the percent complete of one item?
Measure it: installed quantity divided by total quantity, or the share of agreed milestones reached. Write down the basis so the next update uses the same method.